The UK’s National System Energy Operator (NESO) has announced a significant new connections pipeline aimed at accelerating the integration of renewable energy sources into the national grid. This initiative focuses on facilitating the connection of offshore and onshore wind, battery storage, and solar projects that are ready to be integrated into the energy system.

Currently, there are 283 gigawatts (GW) of generation and storage projects in progress, which is approximately five times the peak electricity demand of Great Britain. Of these, 132 GW are directly aligned with the Department for Energy Security and Net Zero’s Clean Power 2030 ambition. In addition to this, there are already 111 GW of capacity connected, creating a robust framework for delivering secure, affordable, and low-carbon electricity to meet future demands.

However, experts caution that the transition from planning to execution presents significant challenges. The previous system, which operated on a ‘first come, first served’ basis, resulted in a backlog of over 5,000 projects totaling approximately 700 GW—far exceeding the grid’s capacity to connect new sources. To address this, the NESO has identified an additional 151 GW of capacity that will be essential by 2035, which could support around 1.5 million fast electric vehicle (EV) chargers.

As demand for electricity rises, nearly 100 GW of new or expanded demand connections from industrial and business users are expected, further driving economic growth and the electrification of various sectors. A recent survey conducted by Aurora Utilities among 800 UK developers and investors revealed that 68% of decision-makers view the NESO’s reforms as an opportunity, with 74% anticipating faster connection times as a result.

Despite this optimism, concerns remain about the potential for a two-tier market that could disadvantage smaller developers. Nearly half of the respondents expressed fears that high connection costs could jeopardize otherwise viable projects. Furthermore, while 60% of developers have committed between £50 million and £250 million for infrastructure projects requiring connections by 2026, a significant portion (33%) already expect to see meaningful project drop-outs during the process.

The survey also highlighted the financial implications of delays, with 60% of respondents indicating that a 12-month delay could increase project costs by 15%. Additionally, 80% warned that supply chain constraints could further disrupt timelines.

Jamie McAinsh, Chief Commercial Officer of Aurora Utilities, emphasized the importance of the NESO reform as a necessary reset for the industry, urging that the delivery system and supply chain must align with the scale of Britain’s ambitious energy goals.

As the UK strives to meet its net zero targets, the success of this new connections pipeline will be crucial in determining the pace and efficiency of the energy transition.

This article was submitted via the World of Renewables press desk.
You can join now and receive a FREE HTML email send to 10,000 contacts of your choice (normally £1,900).

Welcome to WoREA! You are in the right place to learn about all things renewable energy. We would like to take this opportunity to firstly wish you well, congratulate you for being here, but above all else, thank you personally for your interest in renewable energy - we like you! Please feel free to submit your content and/or reach out directly. We are always interested in learning more about our members and the markets in which you work.