Planning Inspectorate makes decision on Kirkby Moor Wind Farm planning appeal

Popular Articles

@WoRenewableshttps://worldofrenewables.com/author/worenewables/
Welcome to WoREA! You are in the right place to learn about all things renewable energy. We would like to take this opportunity to firstly wish you well, congratulate you for being here, but above all else, thank you personally for your interest in renewable energy - we like you! Please feel free to submit your content and/or reach out directly. We are always interested in learning more about our members and the markets in which you work.

The Planning Inspectorate has announced that they will grant planning permission for the continued operation of the Kirkby Moor wind farm until 2027.

Commenting on the decision, Ventient Energy’s CEO Mark Jones said:

“We’re delighted with the decision from the Planning Inspectorate to allow the Kirkby Moor Wind Farm to continue to operate until 2027. This decision echoes the original recommendation of the planning officer and will mean that the wind farm will have permission to continue to deliver clean, green energy for a further eight years.

“We’d like to take this moment to state how grateful we are to the many people in the local community who have supported the appeal, whose voices have played an important part in this positive outcome.

“This decision will see public benefits flow from the development including restoration of parts of the moorland and an enhanced decommissioning, reinstatement and restoration scheme once the life extension period comes to an end and the turbines have been removed.

“Furthermore, the existing community fund will be increased, from its current level of £3,555 per year initially to £24,000 per year in order to bring it in line with current industry best practice guidelines. We look forward to seeing a number of local worthy causes benefit and are excited to see the positive impact this will have on the community going forward,” Jones concludes.

The decision by the Planning Inspectorate overturns the decision made by South Lakeland District Council’s planning committee who rejected the application submitted in 2017 to extend the operational life of the Kirkby Moor Wind Farm and follows a Public Inquiry hearing held in Ulverston in January 2019.