Elements Green Secures Grid Connection for 1.6 GWh Battery Storage Project in Stadorf

November 11, 2026 · · World of Renewables

Elements Green Deutschland GmbH has recently finalised a grid connection agreement with TenneT, the transmission system operator, for its ambitious battery energy storage project located in Stadorf, Lower Saxony. This project, with a planned output of 400 MW and a storage capacity of 1,600 MWh, is set to become one of the largest battery storage facilities in Germany.

Significance of the Agreement

The signing of this grid connection agreement follows the earlier establishment of a connection construction agreement earlier this year, marking a pivotal step forward in the project’s development. Together, these agreements lay the essential contractual groundwork for both the construction and future operation of the grid connection.

The battery energy storage system (BESS) is designed to have a storage duration of four hours and will be directly connected to the extra-high-voltage grid. This capability allows the facility to absorb electricity during periods of high generation or low demand and subsequently release it back into the grid when necessary, thereby enhancing the overall efficiency of the energy system.

Contributions to Renewable Energy Integration

The Stadorf project is poised to play a crucial role in the integration of renewable energy sources into the power grid. By increasing the flexibility of the power system, it aims to make better use of existing energy infrastructure. Michael Zimmermann, Managing Director of Elements Green Deutschland, emphasised the importance of this project, stating, “Signing the grid connection agreement marks another milestone for Stadorf. Together with the connection construction agreement, we now have the key contractual foundations in place for connecting this 400 MW project to the grid. This is significant progress for Elements Green and underlines our ability to successfully advance complex energy infrastructure projects of this scale.”

Strategic Importance of Battery Storage

As Germany continues to transition towards a more sustainable energy landscape, the need for additional renewable generation capacity is paramount. However, equally important is the development of high-performance and flexible infrastructure that can support this transition. Zimmermann noted, “Germany needs not only additional renewable generation capacity but, above all, the high-performance and flexible infrastructure to make the energy transition a technical and economic success. Large-scale battery storage systems such as Stadorf will play a central role in this.”

Future Steps for the Stadorf Project

With the critical grid connection agreements now secured, Elements Green is turning its attention to the next phases of the project. This includes detailed planning of the grid connection infrastructure, preparations for construction, and ongoing coordination with project and technology partners involved in the initiative. The company is committed to ensuring that the project progresses smoothly and efficiently, aligning with its long-term strategy as an integrated developer, investor, and operator of energy infrastructure.

Elements Green’s Broader Vision

The Stadorf project is part of a larger pipeline of battery storage initiatives being developed by Elements Green across Germany. The company is actively working on several large-scale battery storage projects aimed at connecting to the extra-high-voltage grid. This strategic approach underscores Elements Green’s commitment to advancing sustainable energy solutions and contributing to the development of a flexible and robust energy supply system in Germany.

In conclusion, the signing of the grid connection agreement for the Stadorf battery storage project represents a significant advancement in Germany’s energy transition efforts. As the country seeks to enhance its renewable energy capabilities, projects like Stadorf will be instrumental in ensuring a reliable and efficient energy supply for the future.

This article was submitted via the World of Renewables press desk.
You can join now and receive a FREE HTML email send to 10,000 contacts of your choice (normally £1,900).

Project Atlas

Projects connected to this report.

Move directly from the article into the underlying asset, companies and project timeline.

Explore Project Atlas